SCR-Screen demo: IEEE 39-bus scan (assumed data, illustrative costs)

39 plant(s) · 2 group(s) · Rating basis: MW · Source: network model (ieee39_assumed.json), classical flat-start (1.0 pu)
SCR-Screen v0.6.1
2026-11-15 14:48 UTC
MW
Flag thresholds (SCR)
Change any value to recalculate instantly in your browser (per-bus distances and POI costs are editable in the cost table). SCR = SCMVA ÷ plant MW; short-circuit MVA does not change with these inputs. Files exported with --out keep the values the report was created with (1500 MW).
Buses screened
39
Lowest SCR
1.89
Bus 12
Lowest group WSCR
2.20
Group G1
Flagged
6 of 41
EMT priority 1 / 2 / 3
18 / 14 / 7
Lowest N-1 SCR
0.91
Bus 38

Network map

Colors show SCR with all lines and transformers in service.
Network map: buses colored by SCR flagBus 1: SCR 2.94 (weak)Bus 2: SCR 5.87 (none)Bus 3: SCR 4.86 (none)Bus 4: SCR 4.56 (none)Bus 5: SCR 4.71 (none)Bus 6: SCR 4.91 (none)Bus 7: SCR 3.78 (none)Bus 8: SCR 3.88 (none)Bus 9: SCR 2.86 (weak)Bus 10: SCR 4.65 (none)Bus 11: SCR 4.48 (none)Bus 12: SCR 1.89 (very weak)Bus 13: SCR 4.31 (none)Bus 14: SCR 4.44 (none)Bus 15: SCR 4.21 (none)Bus 16: SCR 5.91 (none)Bus 17: SCR 4.95 (none)Bus 18: SCR 4.24 (none)Bus 19: SCR 4.60 (none)Bus 20: SCR 3.35 (none)Bus 21: SCR 4.00 (none)Bus 22: SCR 4.52 (none)Bus 23: SCR 4.12 (none)Bus 24: SCR 4.36 (none)Bus 25: SCR 4.73 (none)Bus 26: SCR 3.52 (none)Bus 27: SCR 3.34 (none)Bus 28: SCR 2.31 (weak)Bus 29: SCR 3.04 (none)Bus 30: SCR 5.98 (none) · generator/source busBus 31: SCR 4.07 (none) · generator/source busBus 32: SCR 4.45 (none) · generator/source busBus 33: SCR 4.36 (none) · generator/source busBus 34: SCR 3.31 (none) · generator/source busBus 35: SCR 4.45 (none) · generator/source busBus 36: SCR 3.61 (none) · generator/source busBus 37: SCR 3.79 (none) · generator/source busBus 38: SCR 4.30 (none) · generator/source busBus 39: SCR 5.87 (none) · generator/source busBus 1 · 2.94Bus 9 · 2.86Bus 12 · 1.89Bus 28 · 2.31
Very weak: below 2Weak: 2 to below 3No flag: 3 or aboveSquare = generator or grid source busDashed line = transformerPulsing ring = every flagged bus; labels = the weakest (up to 8)Hover over a bus for detailsShading spreads each bus's flag color so weak areas stand out; strength is calculated only at buses
Bus positions follow a one-line drawing of this network; they are a drawing, not geographic.

Weakest locations

Lowest SCR in any condition shown. Click a bus here or on the map for its details.

Results

Click a column heading to sort; click a row for the bus details.
BusModel indexGroupSCMVARating (MW)SCRFlagMax size, no flagSCRIFN-1 SCRWorst outageEMT triage
Bus 30298,971.51,500.05.981No flag2,990.51.908Very weakgenerator 0 (Bus 30)Priority 1
Bus 1615G28,865.01,500.05.910No flag2,955.03.579No flag4.412No flagline 21 (Bus 16–Bus 19)Priority 2
Bus 39388,809.01,500.05.873No flag2,936.31.564Very weakgenerator 8 (Bus 39)Priority 1
Bus 218,804.71,500.05.870No flag2,934.93.942No flagtransformer 0 (Bus 2–Bus 30)Priority 3
Bus 1716G27,427.71,500.04.952No flag2,475.92.786Weak2.533Weakline 20 (Bus 16–Bus 17)Priority 2
Bus 657,358.91,500.04.906No flag2,453.03.607No flagtransformer 1 (Bus 6–Bus 31)Priority 3
Bus 327,296.91,500.04.865No flag2,432.32.970Weakline 2 (Bus 2–Bus 3)Priority 2
Bus 25247,090.51,500.04.727No flag2,363.52.348Weakline 3 (Bus 2–Bus 25)Priority 2
Bus 547,064.51,500.04.710No flag2,354.83.459No flagline 8 (Bus 5–Bus 6)Priority 3
Bus 1096,969.41,500.04.646No flag2,323.13.113No flagtransformer 2 (Bus 10–Bus 32)Priority 3
Bus 19186,893.81,500.04.596No flag2,297.92.673Weakline 21 (Bus 16–Bus 19)Priority 2
Bus 436,841.81,500.04.561No flag2,280.63.246No flagline 4 (Bus 3–Bus 4)Priority 3
Bus 22216,785.01,500.04.523No flag2,261.72.817Weaktransformer 8 (Bus 22–Bus 35)Priority 2
Bus 1110G16,712.91,500.04.475No flag2,237.62.528Weak2.837Weakline 11 (Bus 6–Bus 11)Priority 2
Bus 32316,675.11,500.04.450No flag2,225.01.611Very weakgenerator 1 (Bus 32)Priority 1
Bus 35346,670.91,500.04.447No flag2,223.61.757Very weakgenerator 4 (Bus 35)Priority 1
Bus 14136,664.61,500.04.443No flag2,221.53.273No flagline 18 (Bus 14–Bus 15)Priority 3
Bus 24236,545.61,500.04.364No flag2,181.91.218Very weakline 23 (Bus 16–Bus 24)Priority 1
Bus 33326,542.61,500.04.362No flag2,180.91.808Very weakgenerator 2 (Bus 33)Priority 1
Bus 1312G16,470.21,500.04.313No flag2,156.72.397Weak2.612Weakline 16 (Bus 10–Bus 13)Priority 2
Bus 38376,443.01,500.04.295No flag2,147.70.908Very weakgenerator 7 (Bus 38)Priority 1
Bus 18176,359.31,500.04.240No flag2,119.82.125Weakline 24 (Bus 17–Bus 18)Priority 2
Bus 15146,314.81,500.04.210No flag2,104.91.582Very weakline 19 (Bus 15–Bus 16)Priority 1
Bus 23226,173.71,500.04.116No flag2,057.92.420Weakline 27 (Bus 22–Bus 23)Priority 2
Bus 31306,100.31,500.04.067No flag2,033.42.533Weaktransformer 1 (Bus 6–Bus 31)Priority 2
Bus 21206,004.41,500.04.003No flag2,001.52.004Weakline 22 (Bus 16–Bus 21)Priority 2
Bus 875,824.21,500.03.883No flag1,941.43.036No flagline 13 (Bus 8–Bus 9)Priority 3
Bus 37365,689.21,500.03.793No flag1,896.41.586Very weakgenerator 6 (Bus 37)Priority 1
Bus 765,675.71,500.03.784No flag1,891.92.647Weakline 10 (Bus 6–Bus 7)Priority 2
Bus 36355,411.51,500.03.608No flag1,803.81.336Very weakgenerator 5 (Bus 36)Priority 1
Bus 26255,281.31,500.03.521No flag1,760.42.343Weakline 25 (Bus 17–Bus 27)Priority 2
Bus 20195,021.21,500.03.347No flag1,673.71.294Very weaktransformer 5 (Bus 19–Bus 20)Priority 1
Bus 27265,008.81,500.03.339No flag1,669.61.543Very weakline 25 (Bus 17–Bus 27)Priority 1
Bus 34334,965.31,500.03.310No flag1,655.11.321Very weakgenerator 3 (Bus 34)Priority 1
Bus 29284,561.41,500.03.041No flag1,520.51.153Very weaktransformer 10 (Bus 29–Bus 38)Priority 1
Bus 104,410.01,500.02.940Weak1,470.01.228Very weakline 1 (Bus 1–Bus 39)Priority 1
Bus 984,292.61,500.02.862Weak1,430.91.143Very weakline 14 (Bus 9–Bus 39)Priority 1
Bus 28273,461.81,500.02.308Weak1,153.90.974Very weakline 34 (Bus 28–Bus 29)Priority 1
Bus 12112,832.41,500.01.888Very weak944.11.127Very weaktransformer 3 (Bus 12–Bus 11)Priority 1
GroupPlantsTotal rating (MW)WSCRFlagCSCRN-1 WSCRMax total, no flag (MW)
G1Bus 11, Bus 133,000.02.197Weak2.464Weak1.588Very weak2,197.2
G2Bus 16, Bus 173,000.02.715Weak3.204No flag1.747Very weak2,715.5

SCR by bus for a MW plant

SCR, network intactSCR under the worst single outage (N-1)Very weak below Weak below Max, no flag: the largest plant before a weak flag (SCMVA ÷ weak threshold)

Plants screened together (WSCR, CSCR and SCRIF)

Each bus in a group gets a plant of the size above unless you enter its own size in the box. WSCR = Σ(SCMVAᵢ × Pᵢ) ÷ (ΣPᵢ)², assuming the plants are fully interacting (electrically close); for buses far apart this is conservative. CSCR ties the group's points of interconnection together; SCRIF uses the network's interaction factors, so it sits between each plant's SCR and the WSCR. The group's flag and the Flagged count use WSCR, the most conservative. The largest group total keeps the members' sizes in proportion: WSCR × total ÷ weak threshold.

Group G1

Bus 11 aloneMW4.48No flag
Bus 13 aloneMW4.31No flag
Together (WSCR)2.20Weak
Together, POIs tied (CSCR)2.46Weak
Bus 11 with interaction (SCRIF)2.53Weak
Bus 13 with interaction (SCRIF)2.40Weak
Together, worst single outage (N-1 WSCR)line 11 (Bus 6–Bus 11) out1.59Very weak
Largest group total before a weak flag2,197.2 MW intact · 1,588.3 MW N-1
EMT study priority (worst member)Priority 2
Interaction factors IF = |Zrow,col ÷ Zcol,col|: 1.00 means fully interacting (the WSCR assumption), near 0 independent
Bus 11Bus 13
Bus 11—0.77
Bus 130.80—
Screened together, strength is 49% lower than the weakest plant alone.

Group G2

Bus 16 aloneMW5.91No flag
Bus 17 aloneMW4.95No flag
Together (WSCR)2.72Weak
Together, POIs tied (CSCR)3.20No flag
Bus 16 with interaction (SCRIF)3.58No flag
Bus 17 with interaction (SCRIF)2.79Weak
Together, worst single outage (N-1 WSCR)line 20 (Bus 16–Bus 17) out1.75Very weak
Largest group total before a weak flag2,715.5 MW intact · 1,747.4 MW N-1
EMT study priority (worst member)Priority 2
Interaction factors IF = |Zrow,col ÷ Zcol,col|: 1.00 means fully interacting (the WSCR assumption), near 0 independent
Bus 16Bus 17
Bus 16—0.65
Bus 170.78—
Screened together, strength is 45% lower than the weakest plant alone.

Worst single outage (N-1)

Each line circuit and transformer unit was taken out of service in turn; for each bus, the lowest SCR and the outage that causes it. The 12 weakest buses under N-1 are listed; the Results table has every bus.
BusIntact SCRN-1 SCROutage that causes it
Bus 384.2950.908Very weakgenerator 7 (Bus 38)
Bus 282.3080.974Very weakline 34 (Bus 28–Bus 29)
Bus 121.8881.127Very weaktransformer 3 (Bus 12–Bus 11)
Bus 92.8621.143Very weakline 14 (Bus 9–Bus 39)
Bus 293.0411.153Very weaktransformer 10 (Bus 29–Bus 38)
Bus 244.3641.218Very weakline 23 (Bus 16–Bus 24)
Bus 12.9401.228Very weakline 1 (Bus 1–Bus 39)
Bus 203.3471.294Very weaktransformer 5 (Bus 19–Bus 20)
Bus 343.3101.321Very weakgenerator 3 (Bus 34)
Bus 363.6081.336Very weakgenerator 5 (Bus 36)
Bus 273.3391.543Very weakline 25 (Bus 17–Bus 27)
Bus 395.8731.564Very weakgenerator 8 (Bus 39)

EMT study triage

NERC's Reliability Guideline on EMT studies for IBRs (December 2024, Chapter 1) lists situations in which EMT studies should be considered if any one applies, and notes that a high level of system strength alone should not rule out the need for EMT studies. Priorities are SCR-Screen's ordering of the work, not NERC's: 1 = a metric below the very-weak threshold, series compensation, FACTS or HVdc nearby, a system event that positive-sequence models cannot reproduce, or below the OEM minimum SCR; 2 = a metric below the weak threshold, other IBRs nearby, or another situation answered yes; 3 = no screening trigger found. Counts on the card: Priority 1 / 2 / 3.
BusPriorityWhyNot checked
Bus 38Priority 1P1 Low system strength: SCR (N-1) 0.908 is below the very-weak threshold 211
Bus 28Priority 1P2 Low system strength: SCR (intact) 2.308 is below the weak threshold 3 · P1 Low system strength: SCR (N-1) 0.974 is below the very-weak threshold 211
Bus 12Priority 1P1 Low system strength: SCR (intact) 1.888 is below the very-weak threshold 2 · P1 Low system strength: SCR (N-1) 1.127 is below the very-weak threshold 211
Bus 9Priority 1P2 Low system strength: SCR (intact) 2.862 is below the weak threshold 3 · P1 Low system strength: SCR (N-1) 1.143 is below the very-weak threshold 211
Bus 29Priority 1P1 Low system strength: SCR (N-1) 1.153 is below the very-weak threshold 211
Bus 24Priority 1P1 Low system strength: SCR (N-1) 1.218 is below the very-weak threshold 211
Bus 1Priority 1P2 Low system strength: SCR (intact) 2.940 is below the weak threshold 3 · P1 Low system strength: SCR (N-1) 1.228 is below the very-weak threshold 211
Bus 20Priority 1P1 Low system strength: SCR (N-1) 1.294 is below the very-weak threshold 211
Bus 34Priority 1P1 Low system strength: SCR (N-1) 1.321 is below the very-weak threshold 211
Bus 36Priority 1P1 Low system strength: SCR (N-1) 1.336 is below the very-weak threshold 211
Bus 27Priority 1P1 Low system strength: SCR (N-1) 1.543 is below the very-weak threshold 211
Bus 39Priority 1P1 Low system strength: SCR (N-1) 1.564 is below the very-weak threshold 211
Bus 15Priority 1P1 Low system strength: SCR (N-1) 1.582 is below the very-weak threshold 211
Bus 37Priority 1P1 Low system strength: SCR (N-1) 1.586 is below the very-weak threshold 211
Bus 32Priority 1P1 Low system strength: SCR (N-1) 1.611 is below the very-weak threshold 211
Bus 35Priority 1P1 Low system strength: SCR (N-1) 1.757 is below the very-weak threshold 211
Bus 33Priority 1P1 Low system strength: SCR (N-1) 1.808 is below the very-weak threshold 211
Bus 30Priority 1P1 Low system strength: SCR (N-1) 1.908 is below the very-weak threshold 211
Bus 21Priority 2P2 Low system strength: SCR (N-1) 2.004 is below the weak threshold 311
Bus 18Priority 2P2 Low system strength: SCR (N-1) 2.125 is below the weak threshold 311
Bus 26Priority 2P2 Low system strength: SCR (N-1) 2.343 is below the weak threshold 311
Bus 25Priority 2P2 Low system strength: SCR (N-1) 2.348 is below the weak threshold 311
Bus 23Priority 2P2 Low system strength: SCR (N-1) 2.420 is below the weak threshold 311
Bus 31Priority 2P2 Low system strength: SCR (N-1) 2.533 is below the weak threshold 311
Bus 17Priority 2P2 Low system strength: SCR (N-1) 2.533 is below the weak threshold 3 · P2 Low system strength: SCRIF (intact) 2.786 is below the weak threshold 3 · P2 Low system strength: group WSCR (intact) 2.715 is below the weak threshold 311
Bus 13Priority 2P2 Low system strength: SCR (N-1) 2.612 is below the weak threshold 3 · P2 Low system strength: SCRIF (intact) 2.397 is below the weak threshold 3 · P2 Low system strength: group WSCR (intact) 2.197 is below the weak threshold 3 · P2 Low system strength: group CSCR (intact) 2.464 is below the weak threshold 311
Bus 7Priority 2P2 Low system strength: SCR (N-1) 2.647 is below the weak threshold 311
Bus 19Priority 2P2 Low system strength: SCR (N-1) 2.673 is below the weak threshold 311
Bus 22Priority 2P2 Low system strength: SCR (N-1) 2.817 is below the weak threshold 311
Bus 11Priority 2P2 Low system strength: SCR (N-1) 2.837 is below the weak threshold 3 · P2 Low system strength: SCRIF (intact) 2.528 is below the weak threshold 3 · P2 Low system strength: group WSCR (intact) 2.197 is below the weak threshold 3 · P2 Low system strength: group CSCR (intact) 2.464 is below the weak threshold 311
Bus 3Priority 2P2 Low system strength: SCR (N-1) 2.970 is below the weak threshold 311
Bus 16Priority 2P2 Low system strength: group WSCR (intact) 2.715 is below the weak threshold 311
Bus 8Priority 3No screening trigger found11
Bus 10Priority 3No screening trigger found11
Bus 4Priority 3No screening trigger found11
Bus 14Priority 3No screening trigger found11
Bus 5Priority 3No screening trigger found11
Bus 6Priority 3No screening trigger found11
Bus 2Priority 3No screening trigger found11
Not checked: situations a network model cannot show (answer them with --poi-info). For a Thevenin data sheet per POI, use scr-screen triage.
Cost screening

Interconnection cost screening

Plant: 1,500 MWTarget SCR: 3Condenser X″d + Xt: 0.2 + 0.1 puCondenser cost: $100k/MVAGen-tie cost: $2.0M/mileBuses costed: 4 candidate(s) from the site file
1 of 4 bus(es) are below your target SCR of 3: Bus 12. For each, use a plant no larger than its “max at target” size, or add the condenser shown.
Synchronous condenserGen-tie linePOI substation
#BusSCRTarget checkAdded SCMVA neededCondenser MVASCR after condenserCondenser costGen-tie (mi)Gen-tie costPOI cost ($)TotalBreakdown
1Bus 293.04✓ Meets0.00.03.04$0$16.0M$31.0M
2Bus 44.56✓ Meets0.00.04.56$0$24.0M$42.0M
3Bus 121.89Below target
Max at target: 944 MW
or condenser: 500.3 MVA
1,667.6500.33.00$50.0M$8.0M$73.0M
4Bus 165.91✓ Meets0.00.05.91$0$70.0M$90.0M
Condenser MVA = max(0, plant MW × target SCR − SCMVA) × (X″d + Xt). "Incomplete" means a needed part has a quantity but no price entered. Screening-level only. Excludes network upgrades (thermal, voltage, stability), which are often the largest interconnection cost and need power flow and interconnection-queue studies. Condenser sizing assumes the condenser is at the POI with mostly reactive impedances. Grid-forming inverters may mitigate weak-grid conditions at lower cost and are not costed. All costs are user inputs.

Method comparison: Classical vs IEC 60909

Filled dot = Classical; ring = IEC 60909. Highlighted rows: the two methods give a different flag (3 bus(es) at this plant size). Values shown as Classical / IEC 60909.
Bus 30
2
3
5.98 / 6.66
Bus 16
5.91 / 6.55
Bus 39
5.87 / 6.49
Bus 2
5.87 / 6.56
Bus 17
4.95 / 5.48
Bus 6
4.91 / 5.48
Bus 3
4.86 / 5.40
Bus 25
4.73 / 5.28
Bus 5
4.71 / 5.25
Bus 10
4.65 / 5.19
Bus 19
4.60 / 5.11
Bus 4
4.56 / 5.07
Bus 22
4.52 / 5.01
Bus 11
4.48 / 5.00
Bus 32
4.45 / 4.97
Bus 35
4.45 / 4.93
Bus 14
4.44 / 4.94
Bus 24
4.36 / 4.83
Bus 33
4.36 / 4.85
Bus 13
4.31 / 4.81
Bus 38
4.30 / 4.76
Bus 18
4.24 / 4.69
Bus 15
4.21 / 4.66
Bus 23
4.12 / 4.55
Bus 31
4.07 / 4.42
Bus 21
4.00 / 4.43
Bus 8
3.88 / 4.32
Bus 37
3.79 / 4.26
Bus 7
3.78 / 4.21
Bus 36
3.61 / 3.98
Bus 26
3.52 / 3.91
Bus 20
3.35 / 3.75
Bus 27
3.34 / 3.69
Bus 34
3.31 / 3.69
Bus 29
3.04 / 3.41
Bus 1
2.94 / 3.24
Bus 9
2.86 / 3.16
Bus 28
2.31 / 2.57
Bus 12
1.89 / 2.19

Method and assumptions

  • Short-circuit MVA source: network model (ieee39_assumed.json), classical flat-start (1.0 pu). SCMVA excludes the contribution of inverter-based resources, per NERC.
  • SCR = SCMVA ÷ plant rating (MW). WSCR = Σ(SCMVAᵢ × Pᵢ) ÷ (ΣPᵢ)², assuming the plants in a group are fully interacting.
  • Flag bands: below 2 very weak; 2 to below 3 weak; 3 or above no flag. Default bands follow HVDC planning practice (IEEE Std 1204-1997); user-configurable.
  • Bus scan: a hypothetical 1500 MW plant was screened at each bus, one at a time. Buses listed in the groups file were also screened together with WSCR, each with a plant of the same size; WSCR assumes the plants in a group are fully interacting, so group only buses that are electrically close.
  • Bus labels are the bus names in the network file. The Model index column is each bus's position in the file, counting from 0 (so Bus 30 can be index 29).
  • Nominal ratio: 11 transformer(s) have a tap position away from neutral or a rated turns ratio different from the bus voltage ratio; the classical method uses the nominal ratio, so these are not modeled. This is the usual flat-start assumption; it can change the short-circuit MVA by several percent at buses next to those transformers.
  • Group N-1 WSCR: the lowest WSCR when each single outage (the same outages as the N-1 screen) is applied to all members of the group at once, with the members' sizes.
  • SCRIF_i = SCMVA_i ÷ (P_i + Σ IF_ij·P_j), with interaction factors IF_ij = |Z_ij ÷ Z_jj| from the classical network impedance matrix (NERC Reliability Guideline, 2017). CSCR = short-circuit MVA with the group's POIs tied together ÷ total MW; NERC's definition ties the plants' medium-voltage buses, which are not in a transmission model, and divides by the plants' nominal MVA ratings (use --basis MVA to match).
  • N-1: each of 55 line circuits, transformer units and generator units was removed in turn (classical method); the lowest short-circuit MVA at each bus and the outage causing it are shown.
  • EMT triage: NERC (2024, Chapter 1): if any one of the listed situations applies, EMT studies should be considered. NERC (2024, Chapter 1): “having a high level of system strength alone should not rule out the need for EMT studies.” Priorities order the work; they are SCR-Screen's judgment, not NERC's. NERC lists the situations without ranking them. Priority 1: any strength metric below the very-weak threshold in any condition; series compensation, FACTS or HVdc nearby; a system event that positive-sequence models cannot reproduce; or the lowest SCR below the OEM minimum SCR. Priority 2: any strength metric below the weak threshold; other IBRs nearby; or any other situation answered yes. Priority 3: no screening trigger found. In a scan, the conditions are the intact network and the worst single outage.
  • EMT triage, nearby: an existing IBR or device is nearby when max(IF_ij, IF_ji) with the bus is at least 0.5 (--ibr-threshold; SCR-Screen's default judgment value). Series compensation is found as lines with negative series reactance, FACTS as svc/ssc/tcsc and HVdc as vsc/dcline elements. A negative reactance can also be an equivalent branch of a reduced model; answering series_compensation = no in the POI information file tells the triage it is not a series capacitor.
  • EMT triage: no POI information file (--poi-info) was given, so the situations a network model cannot show (e.g. pre-existing oscillation, RAS, system events) are not checked. For a full data sheet per POI, use: scr-screen triage.
References: NERC Reliability Guideline, Integrating Inverter-Based Resources into Low Short Circuit Strength Systems (2017); NERC White Paper, Short-Circuit Modeling and System Strength (2018).

About the live inputs

Change any value to recalculate instantly in your browser (per-bus distances and POI costs are editable in the cost table). SCR = SCMVA ÷ plant MW; short-circuit MVA does not change with these inputs. Files exported with --out keep the values the report was created with (1500 MW).
Screening only. SCR-Screen provides screening-level indicators of system strength. Results do not replace interconnection studies, detailed positive-sequence or EMT analysis, or the requirements of the applicable transmission provider. Thresholds are user-configurable and have no universal validity. SCR-based metrics assume grid-following inverters and do not replace the inverter manufacturer's minimum SCR rating.